Construction without permit and construction without notification in 2023.
Our customers often ask “How fast can a steel hall be built”, and only then are they interested in the price of the structure. This doesn’t surprise us at all – time is increasingly valuable. Not only in business, but also in private investment. We know very well that for our customers the fast construction time of a steel hall is extremely important – to meet these expectations we offer HalMod steel structures, which allow you to build a steel hall at an express pace.
The ability to build a HalMod steel hall even within a few days makesThat our structures are gaining popularity among investors from various industries. However, the construction of the hall itself (or, in fact, its installation) is only one of several stages of the project. See How long does it take to build a steel hall from the design phase to the acceptance of the project.
Need more information? We are happy to answer any questions!
How long does the paperwork for building the hall, or the administrative process, take?
Formalities related to the construction of the hall is the most time-consuming stage of the investment – it can take up to 8 months.
However, in most cases, it can be effectively expedited – our experienced specialists help to prepare the necessary documents and advise on formal and administrative matters.
- Obtaining a local zoning plan from the municipality – up to 12 weeks.
- Analysis of the investor’s concept by our architect – he determines what kind of steel hall can be built on the investor’s plot – up to 2 weeks.
- Once the project is approved by the investor, we can prepare and submit the application for a building permit – 1-2 weeks
- Consideration of the application and enactment of the decision by the authority and the time for the decision to become final – up to 10 weeks.
Summary, the formalities of building the hall may take approx. 6 – 8 months.
We can help investors also make an architectural and construction project, the time for such an order depends primarily on the complexity of the project. It is also worth remembering the need for soil tests – they can be commissioned by the investor or done by us, the waiting time is about a month from the commissioning of the tests.
No paperwork for farmers - see if you can speed up the construction of your agricultural hall.
It is worth remembering that in many cases of investments related to agricultural activities, it is possible to construction of a hall without a building permit, or even without notification. Such simplification of procedures allows you to start building a hall in a much shorter time.
Production of the structure and ordering of additional elements - 3 to 8 weeks
The next stage of steel hall construction is the production of the ordered structure. Once we receive permission and design approval, we can begin manufacturing components to build your steel structure. The manufacturing time of a HalMod steel structure depends on several factors:
- the size of the ordered hall
- dimensions of the hall (standard or individual)
- production occupancy
Typically this stage takes from 3 to 8 weeks, however, we always try to speed up the process as much as possible, especially if we know that the investor cares about time.
While waiting for the steel structure, other stages of the project can be implemented in parallel. At this time, it is a good idea to order any additional elements such as wall and roof cladding – for example.
sandwich panels
,
trapezoidal sheets
, joinery, etc.
The waiting time for these items can be about 4 weeks.
Proper synchronization of work allows to reduce the time of steel hall construction as much as possible.
Earthworks and foundation work - up to 6 weeks
Earthworks and
construction of foundations for steel halls
also can be carried out during the production of the steel structure.
The duration of this stage of work depends on the size of the hall, but also on ground and weather conditions – in case of prolonged rainfall or severe frost, this stage of work may be prolonged. Typically, earthworks alone can be completed in about. 2 weeks. Once this work is completed, it is necessary to pour the foundation and possibly make a foundation for the floor. In most cases comprehensive execution of the foundation slab takes about 5-7 working days, and with small halls this time can be shorter. The parameters of the poured slab are formally obtained 28 days after the work is completed, so it is safer to assume duration of this stage approx. 6 weeks.
How long does it take to install a steel hall structure?
It takes from a few days to 2 weeks to assemble a HalMod modular steel hall.
When the foundations are ready, the installation of the steel structure can begin. Thanks to modular construction and the use of prefabricated components, this stage of hall construction is very fast and efficient. If you use our installation team, Your steel hall can be built in as little as a few days for small agricultural halls, up to 16 days for larger projects.
On the other hand, if you opt for self-assembly, the construction time of the structure depends only on you, and on the availability and commitment of your helpers.
How long does it take to enclose a steel hall?
At this stage of the hall’s construction, the cladding of the walls and the roof with selected materials such as trapezoidal sheet metal or sandwich panels are installed, and the hall acquires its final appearance. Installation of steel hall cladding and carpentry opening work for the installation of doors and windows usually does not take more than 2 weeks, and with small halls it can take up to one day. Such rapid installation work is made possible by the use of matching panels with an easy installation system. Using HalMod’s comprehensive installation service allows you to optimize installation time and Completion of the steel hall in the shortest possible time.
Once the installation is complete, we sign the acceptance report and your steel hall is ready!
Why are HalMod halls being built so quickly?
- complete construction including mounting elements and screws – no downtime due to lack of availability of construction materials
- simple assembly from ready-made elements – no need for special machinery or heavy construction equipment
- installation team – if the investor uses the HalMod installation service, the work goes smoothly and quickly. But even with in-house installation, there is no need to wait for hard-to-reach construction crews – just a few helpers will do.
Finishing and installation work - how long does it take?
If the design of the building included electrical and sanitary installations, interior architecture, landscaping plan in front of the building, we can advise you on choosing the right service providers and suggest what to pay attention to when making arrangements with technical teams. The duration of this phase of work depends on the complexity of the project and the availability of teams, so it is difficult to estimate.
How to optimize the construction time of a steel hall?
Of course, using HalMod’s products and comprehensive services! Remember, too, that you also have a say in the pace of your steel hall construction! If the investor is committed and available, all design arrangements and installation work will proceed smoothly and quickly.
Modular design, fast production of elements and comprehensive formal and technical support are the guarantee of express construction of your steel hall – warehouse, agricultural, production or garage, for any industry.
HalMod’s fast construction of steel halls gives investors a competitive edge and the ability to respond quickly to the need to build or expand production or warehouse space. Quick construction time is also an advantage of steel halls over masonry halls – check it out differences between a steel hall and a masonry hall.